You need to update the project with time worked per day

You are tracking a project in Microsoft Office Project Standard 2007. You need to update the project with time worked per day. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Enter Work in a task view.

B.
Enter Actual Start in an assignment view.

C.
Enter Actual Work in an assignment view.

D.
Enter Physical % Complete in a task view.