you need to identify which tasks are behind schedule

You are tracking a project in Microsoft Office Project Standard 2007. In the Gantt Chart view, you need to identify which tasks are behind schedule. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Sort the tasks by start date.

B.
Group the tasks by completion status.

C.
Set the status date to the current date, and then display a progress line.

D.
Set the status date to the current date, and then open the Project Statistics dialog box.