You need to create a dynamically numbered representation of the project task hierarchy structure, for use in v

You are working with a project schedule in Microsoft Office Project Standard 2007. Your organization uses customized alphanumeric WBS codes to integrate your project schedules and the accounting system. You need to create a dynamically numbered representation of the project task hierarchy structure, for use in views and reports. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Activate the Show Outline Symbol option.

B.
Insert the Outline Level field into the views and reports.

C.
Insert the Outline Number field into the views and reports.

D.
Create a custom Task Outline Code field, and use itto number your tasks.