you need to ensure that resources are not over-allocated, by using the method that gives you the most control

You are creating a project plan in Microsoft Office Project Standard 2007. Your organization does not allow resources to work overtime. Every time you make a change to your schedule, you need to ensure that resources are not over-allocated, by using the method that gives you the most control.
What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Manually level the entire schedule.

B.
Set the schedule to automatically level.

C.
Set all tasks to a priority level of 1000, and then set the schedule to clear leveling values before leveling.

D.
Set the project summary task to a priority level of 1000, and then set the schedule to adjust individual assignments before leveling.