PrepAway - Latest Free Exam Questions & Answers

You need to set the Task Mode for task 4 to be the same as task 6

You manage a project according to the schedule as shown in the exhibit. (Click the Exhibit
button.)

You need to set the Task Mode for task 4 to be the same as task 6. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Create a task dependency from Task 4 to Task 6.

B.
Set Task 4 as critical.

C.
Add a 1 day lead to Task 4.

D.
Set Task 4 as manually scheduled.

6 Comments on “You need to set the Task Mode for task 4 to be the same as task 6


Leave a Reply