PrepAway - Latest Free Exam Questions & Answers

You need to see the project start and finish dates and the task start and finish dates on the table side of th

You create tasks in a project plan in Microsoft Office Project Standard 2007. You need to see the project start and finish dates and the task start and finish dates on the table side of the Gantt Chart view. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Display the Work table.

B.
Display the Schedule table.

C.
Display the project summary task.

D.
Generate the default project summary overview report.


Leave a Reply