You need to reconfigure Tasks to be a milestone

You have a task named Tasks that has a duration of four days and a finish-to-finish
relationship with a task named Task4. You need to reconfigure Tasks to be a milestone. You
also need to retain the original duration and resource assignments. You select Tasks. What
should you do next?

PrepAway - Latest Free Exam Questions & Answers

A.
Remove the predecessor assignments.

B.
Click the Insert Milestone button.

C.
Select the Mark Task as Milestone check box.

D.
Change Work to zero hours.