You need to maintain ownership and authority of key program dates at the program level

You are a program manager for an organization that uses Project Server 2013.
You are responsible for implementing a data warehouse that compiles relational data from many
business areas. Your project managers need to be able to manage the implementation for a business
area as separate projects, while still recognizing the dependencies at a program level.
You need to maintain ownership and authority of key program dates at the program level.
What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Create one project file for all project managers that includes the program-level tasks and each
sub-project’s tasks. Require each area project manager to share the file, and add their dependencies
within their own tasks.

B.
Create and publish a master project file with general durations for each business area sub-project,
and have the area project manager reconcile the dates in their own project manually each week.

C.
Have the project managers create, save, and publish sub-projects for each area. Then insert them
into a program-level project, define dependencies, and save and publish the program-level project to
the server.

D.
Create a master project and insert your projects, but never publish the file on the server.