You need to ensure resources cannot provide status on phase three assignments

Your organization uses Project Server 2013. Your environment’s default task mode is auto scheduled.
Your environment allows manually scheduled tasks to be displayed in Project Web App (PWA).
You create a detailed enterprise project with resources assigned to auto scheduled tasks. Your
project has three phases, but only the first two phases have been approved to begin work.
You need to ensure resources cannot provide status on phase three assignments.
What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Change all tasks in phase three to manually scheduled tasks.

B.
Change the Confirmed field for all tasks in phase three to No.

C.
Change the Publish field for the tasks in phase three to No.

D.
Change the Publish field for all tasks in phase three to Yes.