What should you do?

You are a project manager for an organization that uses Project Server 2013. You have the default
Project Server security permissions and can modify your Project Site.
Your project schedule has a Project Site, which includes a Document Library that contains some
standard documents and a calendar view used only for project meetings.
You need a separate calendar view to track team members’ vacation dates.
What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
In the Project Server 2013 Project Site, use the Add Lists, Libraries, or Apps button and create a
new Calendar.

B.
Ask the Project Server administrator to elevate your permissions and give you the ability to create
a new calendar.

C.
Ask the Project Server administrator to create your desired Calendar view and add it to the default
Project Site.

D.
In Project Professional 2013, create a new Calendar view for the schedule. The next time you
publish the schedule, the new Calendar view will be available in the Project Site.