Which four actions should you perform in sequence?

DRAG DROP
You are a program manager with administrator rights/ and you use Project Server 2013 to
implement a data warehouse.
You set up your program master project with sub-projects for each implementation area.
You need to use the Project Center view to create a custom view of the data warehouse projects for
your vice president.
Which four actions should you perform in sequence? (To answer, move the appropriate four actions
from the list of actions to the answer area and arrange them in the correct order.)