Which element should you use?

Your organization is performing a Portfolio Analysis in Project Server 2013.
You want to create a consolidated Portfolio Analysis optimization based on Cost and Resource data,
which will be part of the project information in Project Server 2013.
You plan to provide different simulations to your organization by using those parameters and
returning the best prioritization.
This organization has two different unit directors, who have the final decision on the consolidated
Portfolio Analysis results.
You need to provide the ability for your unit directors to modify the final portfolio selection.
Which element should you use?

A project manager calls you to report they are unable to open your project for edit in PW

You are a project manager in an organization that uses Project Server 2013. All project managers
have permission to edit all projects.
You edit a project in Project Web App (PWA), make changes, publish the project, and close your
browser.
A project manager calls you to report they are unable to open your project for edit in PWA.
You need to resolve this issue. What should you do?

You need to generate a solution that allows R&D to gather their ideas and facilitate the materialization i

Your organization is a multinational corporation that uses Project Online to plan and control the
projects in different business units. Each business unit has its own portfolio of projects but can
participate in strategic projects.
The Research and Development (R&D) department has been struggling to gather and materialize the
new ideas. The Project Management Office (PMO) has the necessary templates and Enterprise
Project Types (EPTs) to start a formal process for any new product and to adhere to the general
guidelines. However, the R&D group does not want to register all of their ideas since many are
related to improvements and few of them could be materialized into projects.
You need to generate a solution that allows R&D to gather their ideas and facilitate the
materialization into Enterprise Projects.
What should you do?

You need to guarantee that the analysis will produce the most viable proposal in terms of cost and resources a

Your organization uses Project Online for project portfolio selection. The business drivers and
priorities are set, as are the main constraints to identify the efficient frontier.
The company has been collecting business cases for new proposals in which many projects may solve
the same business need. For example, the selection for a Customer Relationship Management
system has six different proposals, whereas only one is necessary to fulfill the business need.
You need to guarantee that the analysis will produce the most viable proposal in terms of cost and
resources and that no repetitive efforts exist in the portfolio selection.
What should you do?

You need to maintain ownership and authority of key program dates at the program level

You are a program manager for an organization that uses Project Server 2013.
You are responsible for implementing a data warehouse that compiles relational data from many
business areas. Your project managers need to be able to manage the implementation for a business
area as separate projects, while still recognizing the dependencies at a program level.
You need to maintain ownership and authority of key program dates at the program level.
What should you do?

What are two possible ways to achieve this goal?

You are a program manager for a company that uses Project Server 2013 and Project Professional
2013. You manage the implementation of a data warehouse.
You have set up your program master project with subprojects for each implementation area.
You need to make edits to the dependencies between projects.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution.
Choose two.)

You need to gather general information about the new product by efficiently collaborating with the local team

Your work in a multinational corporation which uses Project Server 2013 to plan and control projects
in different business units. Each business unit has its own portfolio of projects but can participate in
strategic projects. The Project Management Office (PMO) has configured Enterprise Project Types
(EPTs) to create new products, launch marketing campaigns, and deploy new lines of business tools
to comply with the governance processes.
One of your roles is to identify new products. A local team in Singapore produces an effective idea
for a new product.
You need to create a business case for the next portfolio analysis. You need to gather general
information about the new product by efficiently collaborating with the local team.
What should you do?

You need to return with a valid set of drivers and prioritization to perform the analysis

Your organization has implemented Project Server 2013 to plan and control enterprise projects.
Your organization plans to perform a Portfolio Analysis for the first time on the Selection of Projects
to be done the next year. Business drivers, as well as a pair wise comparison of those business
drivers to set the business priorities, is the chosen method.
Your organization has provided you with a total of 35 business drivers, 30 of which are related in
some way.
You need to return with a valid set of drivers and prioritization to perform the analysis.
What should you do?

What are two possible ways to achieve this goal?

You are a manager for a project your team has been working on for many weeks. Your project is
created as a Microsoft SharePoint task list project and is available in Project Center.
You have established the work breakdown structure (WBS), predecessors, assignments, and all of
the functionalities you can get from a SharePoint task list. However, the project has grown in detail,
and managing 200 activities has become difficult in Project Web App (PWA).
You need to ensure resources continue to report their progress in the same way.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution.
Choose two.)

Which two actions should you perform?

A company deploys Project Server 2013 to perform a Portfolio Analysis, which they will use to select
the projects they will execute in the next fiscal period.
The company establishes the criteria to evaluate the portfolio components, and all business cases
must be evaluated under these parameters. When configuring Project Server 2013, the Project
Management Office (PMO) finds that the established criteria contain both qualitative and
quantitative elements, such as corporate reputation and internal rate of return (IRR).
You need to provide a system calculated approach to rank your strategic initiatives against each
other. Which two actions should you perform? (Each correct answer presents part of the solution.
Choose two.)