You need to identify these tasks as critical

A project that you are tracking in Microsoft Office Project Standard 2007 has tight deadlines that must be met. For some tasks, a delay of more than 5 days will impact the project end date. You need to identify these tasks as critical. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Insert the Critical column into the Gantt Chart view.

B.
Filter the project schedule to display only tasks slipping by more than 5 days.

C.
Filter the project schedule to display only tasks with more than 5 days of free slack.

D.
In the calculation options, set the number of days of slack to less than or equal to 5 days for critical tasks.