You need to disable the automatic creation of predecessors and successors

You plan the next phase of a project in more detail by creating new tasks in an existing project plan. You insert a new task between two existing tasks. Microsoft Office Project Standard 2007 automatically creates a predecessor and successor. You need to disable the automatic creation of predecessors and successors. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Turn off the autolink option.

B.
Calculate multiple critical paths.

C.
Delete links that you do not need.

D.
Enable the manual calculation mode.