You need to ascertain the late finish of Task 4

You are tracking a project in Microsoft Office Project Standard 2007. The project follows the plan shown below: You need to ascertain the late finish of Task 4. What is the result?

PrepAway - Latest Free Exam Questions & Answers

A.
The end of Week 1.

B.
The end of Week 2.

C.
The end of Week 3.

D.
The end of Week 4.