Which two actions should you perform? (Each correct answer presents part of the solution

You are managing a project schedule in Microsoft Office Project Standard 2007. The schedule includes tasks that require a variety of resources. You need to display only the tasks that use role- based resources, grouped by the resource to which they are assigned. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

PrepAway - Latest Free Exam Questions & Answers

A.
Filter the view by resource name.

B.
View the tasks in the Task Entry view.

C.
View the tasks in the Resource Usage view.

D.
Apply a custom filter to display generic resources.

E.
Apply a custom filter to display non-generic resources.