PrepAway - Latest Free Exam Questions & Answers

Which tracking method should you use?

You work for an organization that uses Project Server 2013. Single-entry mode is disabled.
Team members enter updates in Project Web App (PWA) through the Tasks page. You need to select
a tracking method that enables the following scenario:
• During week one, a team member enters a total of 20 hours of actual work.
• During week two, the team member modifies the total to 30 hours of actual work.
• Following a save, the work value remains the same, and the remaining work value
decreases.
• Additionally, the percent of work complete increases.
Which tracking method should you use?

PrepAway - Latest Free Exam Questions & Answers

A.
Percent of work complete

B.
Actual work done and work remaining

C.
Hours of work done per period

D.
Report hours worked every day


Leave a Reply