Your project schedule contains both Work and Material resources. The resources are
assigned to tasks and are of either the committed or proposed booking type. You need to
ensure that the project does not contain over-allocated resources. Which feature should you
use?

PrepAway - Latest Free Exam Questions & Answers

A.
Clear Leveling

B.
Assign Resources

C.
Resource Pool C Share Resources

D.
Level All