PrepAway - Latest Free Exam Questions & Answers

In the Resource Usage view, what should you do?

You are tracking a project schedule in Microsoft Office Project Standard 2007. You need to track overtime worked during each week of a project. In the Resource Usage view, what should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Display the Work table.

B.
Add the Actual Overtime Work row.

C.
Modify the view from the View Definition dialog box.

D.
Add the Overtime Work column to the Usage table.


Leave a Reply