You are working on ____.

You are the project manager for ABC project. You are planning for when and how human resource
requirements will be met. You are working on ____.

PrepAway - Latest Free Exam Questions & Answers

A.
Scope management plan

B.
Project organization chart

C.
Staffing management plan

D.
Resource calendar

Explanation: