What type of risk response is being audited in this scenario?

You are the project manager of the NHQ project for your company. You are working with your
project team to complete a risk audit. A recent issue that your project team responded to, and
management approved, was to increase the project schedule because there was risk surrounding
the installation time of a new material. Your logic was that with the expanded schedule there would
be time to complete the installation without affecting downstream project activities. What type of
risk response is being audited in this scenario?

What risk identification method could you use?

Your project spans the entire organization. You would like to assess the risk of the project but are
worried that some of the managers involved in the project could affect the outcome of any risk
identification meeting. Your worry is based on the fact that some employees would not want to
publicly identify risk events that could make their supervisors look bad. You would like a method
that would allow participants to anonymously identify risk events. What risk identification method could you use?