What portion of the project will you most likely use for probability distributions?

Ned is the project manager of the HNN project for your company. Ned has asked you to help him
complete some probability distributions for his project. What portion of the project will you most
likely use for probability distributions?

PrepAway - Latest Free Exam Questions & Answers

A.
Uncertainty in values such as duration of schedule activities

B.
Risk probability and impact matrixes

C.
Bias towards risk in new resources

D.
Risk identification

Explanation: