Gary has identified a project risk that could injure project team members. He does not want to
accept any risk where someone could become injured on this project so he hires a professional
vendor to complete this portion of the project work. This workaround to the risk event is known as
what type of risk response?

PrepAway - Latest Free Exam Questions & Answers

A.
Avoidance

B.
Mitigation

C.
Acceptance

D.
Transference

Explanation: