Which of the following will the project manager use to determine the budgeted cost of work scheduled?

A project manager is managing a project that is scheduled to take ten months to complete. The project is in its sixth month and $450,000 has been spent. The project budget is $990,000. Which of the following will the project manager use to determine the budgeted cost of work scheduled?

PrepAway - Latest Free Exam Questions & Answers

A.
Estimate to completion

B.
Planned value

C.
Cost performance index

D.
Budget at completion