Changing the project schedule to prevent a known risk is an example of which of the following risk responses?

Changing the project schedule to prevent a known risk is an example of which of the following risk responses?

PrepAway - Latest Free Exam Questions & Answers

A.
Mitigation

B.
Avoidance

C.
Acceptance

D.
Transference