A project manager has received a change request. Which of the following is the NEXT step?

PrepAway - Latest Free Exam Questions & Answers

A.
Approve the change and notify the project sponsor that cost can be reduced.

B.
Re-baseline the project budget because this change will decrease the expenditures.

C.
Send the change to the project sponsor for approval.

D.
Analyze the change to determine the impact.