During which of the following process groups is the preliminary project risk assessment performed?

During which of the following process groups is the preliminary project risk assessment performed?

PrepAway - Latest Free Exam Questions & Answers

A.
Monitoring/Controlling

B.
Planning

C.
Initiating

D.
Executing