A project manager was called into the office of the Chief Information Officer (CIO) and informed that the resource budget for the company has been reduced by 10%. The CIO expects that the project must be completed on time.
Which of the following will be impacted?

A.
Project scope will be impacted.
B.
Quality will be impacted.
C.
WBS will be impacted.
D.
SOW will be impacted.