PrepAway - Latest Free Exam Questions & Answers

Which of the following is included in the project scope document? (Select TWO)

Which of the following is included in the project scope document? (Select TWO).

PrepAway - Latest Free Exam Questions & Answers

A.
Quality metrics

B.
Work packages

C.
Assumptions

D.
Constraints

E.
Resource requirements


Leave a Reply