An organization experienced a fire at its datacenter and was unable to operate at that location. The company moved to a location where HVAC and power are
available, but must supply and configure its own computing resources in order to provide services. The company has relocated to a:

A.
hot site
B.
co-location site
C.
warm site
D.
cold site
I’m thinking about this questions, why is not Warm and got answer on this:
“A warm backup site is already stocked with hardware representing a reasonable facsimile of that found in your data center.”
This is keyword already stocked with hardware..
I pick Cold site, D.