At a project milestone meeting, the project sponsor asked about a deliverable that is not on the project plan. Which of the following should the project manager do to compensate for this unmet expectation?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Review the scope with the vendor.
B.
Review the scope with the customer.
C.
Review the scope with the team.
D.
Review the scope with the sponsor.