A project team member is uncertain how many activities are required to complete a task. Which of the following documents should be referenced?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Key Performance Indicators (KPIs)
B.
Project charter
C.
Work Breakdown Structure (WBS)
D.
Statement of Work (SOW)