Which four physical connections on a fabric interconnect are needed to perform the initial system setup for a

Which four physical connections on a fabric interconnect are needed to perform the initial system
setup for a cluster configuration? (Choose four.)

PrepAway - Latest Free Exam Questions & Answers

A.
Ethernet uplink ports connected to upstream switch

B.
console port connected to a computer terminal or console server.

C.
Layer 1 ports on both fabric interconnects connected to each other

D.
Layer 1 port of the first fabric interconnect connected to Layer 2 port of the second fabric
interconnect

E.
Layer 2 ports on both fabric interconnects connected to each other

F.
Fibre Channel uplink ports connected to upstream fabric switch

G.
management Ethernet port (mgmt0) connected to external switch or router

H.
port channel to each fabric interconnect