Which scheduling option sets the number of tasks that can be run?
A. max number of concurrent tasks
B. max changes
C. max number of tasks
D. max configuration requests
One Comment on “Which scheduling option sets the number of tasks that can be run?”
joaosays:
Answer is C
By default, the maximum duration is set to none. If you do not change this setting and you do not set a maximum number of tasks, the maintenance window continues until all pending activities are completed.
Answer is C
By default, the maximum duration is set to none. If you do not change this setting and you do not set a maximum number of tasks, the maintenance window continues until all pending activities are completed.
http://www.cisco.com/c/en/us/td/docs/unified_computing/ucs/ucs-manager/GUI-User-Guides/Admin-Management/3-1/b_Cisco_UCS_Admin_Mgmt_Guide_3_1/b_Cisco_UCS_Admin_Mgmt_Guide_3_1_chapter_01010.html