Which of the following techniques uses historical information to estimate the activity duration?
Which of the following techniques uses historical information to estimate the activity duration?
What is a specific advantage of analogous estimating in comparison with other cost estimate techniques?
What is a specific advantage of analogous estimating in comparison with other cost estimate techniques?
Which of the following is an output of the Estimate Activity Resources process?
Which of the following is an output of the Estimate Activity Resources process?
In the precedence diagramming method, which of the following is a logical relationship for the activities?
In the precedence diagramming method, which of the following is a logical relationship for the activities?
During the initial stages of the project, what do activity attributes include?
During the initial stages of the project, what do activity attributes include?
What tool or technique of Estimate Activity Durations uses parameters such as duration, budget, size, weight
What tool or technique of Estimate Activity Durations uses parameters such as duration, budget, size, weight, and complexity from a previous, similar project as the basis for estimating the same parameter or measure for a future project?
Which schedule format usually shows both the project network logic and the project’s critical path sched
Which schedule format usually shows both the project network logic and the project’s critical path schedule activities with activity date information?
Which is the total float for the activity G?
Which is the total float for the activity G?
Which of these are logical dependencies in a precedence diagram method?
Which of these are logical dependencies in a precedence diagram method?
what is the expected duration in which the activity will be completed?
In the three-point estimating technique, if the most likely estimate for an activity to complete is 100 days, the optimistic estimate is 60 days, and the pessimistic estimate is 200 days, what is the expected duration in which the activity will be completed?