The customer wants to assign users to VLANs dynamically based on their Windows group. The
company Windows Network Policy server provides the assignments. Each of the Windows groups
includes between 100 to 600 users.
Which issue does the architect need to resolve?

PrepAway - Latest Free Exam Questions & Answers

A.
The proposed dynamic VLANs have too many potential users for the proposed subnets.

B.
The plan for the edge ports is incorrect they should be trunk ports that support multiple VLANs.

C.
The switch-to-switch links should not carry so many VLANs.

D.
The proposed switches do not accept dynamic VLAN assignments from Windows NPS servers.