What is the definition of Recovery Point Objective (RPO)?

What is the definition of Recovery Point Objective (RPO)?

PrepAway - Latest Free Exam Questions & Answers

A.
point in the process code that needs to be recovered

B.
amount of time a recovery process must wait before it can be initiated

C.
amount of time a recovery process may take

D.
amount of data that can be unrecoverable

Explanation:

http://en.wikipedia.org/wiki/Recovery_point_objective#RPO_and_RTO-_a_worked_example
A “recovery point objective” or “RPO”, is defined by business continuity planning. It is the
maximum tolerable period in which data might be lost from an IT service due to a major incident

The above figure is an example of how RPO and RTO might pan out in a practical situation. Tape
is used for backup in this example. The tapes are sent offsite once per day at around the same
time, but this timing is not fully guaranteed. The offsiting operation does happen to occur at
roughly the same time of day in the chart above. The daily backup offsiting tasks in this example
are as follows:

A set of backups are made to tape, possibly via a disk staging area. The synchronisation point for
each set of backups is late in the backup operation in this example as several large databases
have to be backed up and all of them are required for a Synchronisation Point (this is typical of
such systems).
After that the tapes have to be ejected, collated, and catalogued as they are boxed. It is often the
case that offsiting operations are batched across a wide spectrum of systems at a data centre;
generally the backups for all services have to wait for the very last one to be created and boxed
before they can be sent to the loading bay for transport.
Pickups by offsite data repositories are expensive. Generally a daily pickup with a reasonably
priced contract will have only an approximate time for pickup and will be predicated on the data
centre being ready with the tapes when the van turns up- extra pickups will be generally too
expensive to contemplate on a regular basis so a data centre must build contingency time into the
preparation period before the pickup is due to occur.
All of which must be done before the pickup- and all of which must be included in the RPO
calculation because the synchronisation point being sent offsite depends on backups that were
started very near to the start of these activities. So: a recovered service, after a restore from one
of these daily backups, will be very likely to start up as at the end of the online day perhaps 13 or
so hours or more, before the restored tapes were driven away from the Production data centre.
Against this background, suppose that a Major Incident occurs just before an offsiting pick up
(worst case) and as always the assumption is “total site loss, instantly”- so the prepared backups
never leave the site. In this case the RPO is set to 48 hours- only twice the normal offsiting cycle.
As it happens, on this occasion pickups have been regular for a while and you might make the
mistake of thinking that because two offsiting operations have occurred within the RPO period
noted above, you have two sets of tapes you might be able to use and still be within the RPO. This
is not the case- the earlier set of tapes will produce a recovered service as at a recovery point that
is much older than it needs to be to meet the 48 hour RPO. In this example perhaps 12 or 13
hours over that time. In this example, consider the effect of the latest set of offsited tapes being
rendered useless by a critically defective tape in the set (perhaps a 5-10% chance?)- as you can
see by the example above, you can now NOT meet the RPO at all. Tape capacity is increasing all
the time- potentially, fewer tapes mean that individual tape defects damage more backed up data.
To complete the picture, the RTO is noted above too. In this case the service was recovered well
before the RTO limit was hit. It is however interesting to contemplate the fact that in this example
the RTO does NOT start just after the Major Incident. In this example, as often there is in reality,
there is seemingly too much delay. A quick decision to go to invocation of the ITSC Plan is always
the best decision; in principle… The rule in setting an RTO should be that the RTO is the longest
period of time the business can do without the IT Service in question. On the back of this

appropriately economic decisions must be taken at the design stage about how the IT Service is
built and run. It must be allowed however that some time has to be spent in making the decision to
invoke the ITSC Plan, this decision time is an unknown variable- remember too there are often
quite large sums of money spent immediately the decision to invoke is taken- staff being called in
for extended periods of 24 hour working cover and large fees charged by some recovery service
providers at the outset of recovery. In the example, there is the almost inevitable fudge that the
RTO is set to the maximum time the business can do without the service whilst knowing full well
that there is very likely to be a period of decision making before it.