you need to set up a process so that available service personnel can assign themselves to the next unassigned

As a service manager, you are responsible for service requests. Working in Microsoft Office Project Web Access, you need to set up a process so that available service personnel can assign themselves to the next unassigned request. First, you create an activity plan. What should you do next?

PrepAway - Latest Free Exam Questions & Answers

A.
Create the tasks, and then assign each task to a resource.

B.
Create the tasks, and then assign all the tasks to a resource team.

C.
Create a resource plan, but do not assign any tasks to resources.

D.
Publish the activity plan, and then direct resources to reassign work.