You need to record the hours you work on assigned tasks

You are assigned to tasks in projects and in non-project activities that are published to Microsoft Office Project Server 2007. You need to record the hours you work on assigned tasks. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
In Microsoft Office Project Web Access, on the My Tasks page, create a new task for each task and activity.

B.
In Microsoft Office Project Web Access, create a timesheet for all projects worked on in the current period.

C.
In Microsoft Office Project Web Access, create a timesheet for all tasks worked on in the current period.

D.
In Microsoft Office Project Professional 2007, enter your work hours directly into the project.