You need to display the differences between dates for program milestones and project milestones when they chan

In Microsoft Office Project Professional 2007, your program manager has created a program schedule with a Deliverables list representing key milestones. You need to display the differences between dates for program milestones and project milestones when they change. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Copy the program milestones to the Deliverables list of the project workspace site.

B.
Manage dependencies on deliverables, and create a link to a task.

C.
Manage dependencies on deliverables, but do not create a link to a task.

D.
Insert your project and the program schedule into a master project, and then create start-to-finish dependencies between tasks for project and program milestones.