You receive a status report from your project team on the first Monday of each month. You now want the team to provide a status report every Monday instead. In Microsoft Office Project Web Access, you need to receive a single weekly status report, while retaining the old monthly reports. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Create a new status report request with weekly frequency.

B.
Edit the status report request, changing the frequency to weekly.

C.
Delete the old status report request, and create a new request with weekly frequency.

D.
Create a new status report request with a frequency of every second Monday, another with a frequency of every third Monday, and another with a frequency of every fourth Monday.