PrepAway - Latest Free Exam Questions & Answers

Which two actions could you perform?

You have a list of tasks in Microsoft Excel 2010. You need to create a Microsoft Project 2010 schedule that maintains the order of the tasks. Which two actions could you perform? Each correct answer presents a complete solution.

PrepAway - Latest Free Exam Questions & Answers

A.
From Excel 2010, save the file by using the .mpp file extension.

B.
From Project 2010, use the New from Excel workbook wizard.

C.
From Project 2010, use the Open command and select the Excel file.

D.
From Excel 2010, save the file by using the .mpt file extension.

Explanation:
From Excel 2010, you cannot save as .mpp or .mpt