Which set of values describes the specified task?

Standard working hours are eight hours a day from Monday through Friday. You create a task of fixed units and set the duration to 2 days. You assign the task to John at 100 percent. John wants to work only 50 percent on the task. You change Johns assignment units to 50 percent for the task. Which set of values describes the specified task?

PrepAway - Latest Free Exam Questions & Answers

A.
Duration shows 2 days; Work shows 0 hours

B.
Duration shows 4 days; Work shows 16 hours

C.
Duration shows 4 days; Work shows 8 hours

D.
Duration shows 2 days; Work shows 8 hours

E.
Duration shows 2 days; Work shows 16 hours