You have team members who work on one of the following shifts: Monday through Friday: 8 hours a day. Tuesday through Saturday: 10 hours a day. Sunday through Wednesday: 12 hours a day. You need to ensure that your project plan accommodates the different shifts. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Create shift resource departments.

B.
Change the maximum units for each resource.

C.
Create three tasks, one for each shift.

D.
Create a base calendar for each shift.