PrepAway - Latest Free Exam Questions & Answers

What percentage of units should be reflected in the schedule by Adam’s workload?

DRAG & DROP
You use Microsoft Project Professional 2010 to manage an engineering project according to the schedule as shown in the exhibit. Originally, Adam Barr was assigned 75 percent units for 3 days. Adam worked for 8 hours on the first day and informed you that he needs an additional 9 hours of work to finish. You update the schedule. What percentage of units should be reflected in the schedule by Adam’s workload?

PrepAway - Latest Free Exam Questions & Answers

A.
75%, 75%

B.
75%, 100%

C.
100%, 100%

D.
100%, 150%


Leave a Reply