You need to achieve this goal while retaining manually scheduled tasks within the project
You create several new tasks by using the Manually Scheduled Task option. You need to
automatically calculate the start and finish dates for linked manually scheduled tasks. You
need to achieve this goal while retaining manually scheduled tasks within the project. What
should you do?
You need to identify the dates on which the over-allocation occurs
You use Project Professional 2010 to manage a project. John, a team member, is overallocated. You need to identify the dates on which the over-allocation occurs. What should
you do?
You need to assign the task to the resource without scheduling the task
You have an unscheduled, unassigned task in your Project Professional 2010 schedule. You
identify an available resource. You need to assign the task to the resource without
scheduling the task. What should you do?
You need to be able to identify a possible resolution for the over-allocated resources
You are reviewing the task details of your project. You receive the following warning
message:
“This task has resources assigned which are over-allocated.”
You need to be able to identify a possible resolution for the over-allocated resources.
What should you do?
You need to track task-level airfare costs that do not depend on the amount of work or duration of a task
You track all costs on your project. You need to track task-level airfare costs that do not
depend on the amount of work or duration of a task. What should you do?
Which feature should you use?
Your project schedule contains both Work and Material resources. The resources are
assigned to tasks and are of either the committed or proposed booking type. You need to
ensure that the project does not contain over-allocated resources. Which feature should you
use?
You need to update the project schedule to reflect the change
John, a team member, will be absent from the team. A new team member, Mary, will take
over Johns remaining work. You need to update the project schedule to reflect the change.
You also need to retain John’s actual work. What should you do?
You need to ensure that project costs automatically adjust for these resources
Your project has some resources with rates that adjust over time. You need to ensure that
project costs automatically adjust for these resources. What should you do?
Which set of values describes the specified task?
Standard working hours are eight hours a day from Monday through Friday. You create a
task of fixed units and set the duration to 2 days. You assign the task to John at 100 percent.
John wants to work only 50 percent on the task. You change John’s assignment units to 50
percent for the task. Which set of values describes the specified task?
You need to replace the resource assignment for an in-progress task
You need to replace the resource assignment for an in-progress task. You also need to
retain the Work, Actual Work, Remaining Work, and Baseline data for the task. What should
you do?