In a project that is published to Microsoft Office Project Server 2007, a task cannot start until a task in another project is completed. You need to display any delay of the preceding task without the succeeding task being automatically rescheduled. What should you do?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Link the tasks with a finish-to-finish dependency.
B.
Link the tasks with a start-to-finish dependency.
C.
Use a temporary master project plan to link the tasks.
D.
Link the task to a deliverable in the preceding project plan.