You have a list of tasks to manage by using Microsoft Office Project Server 2007. In Microsoft Office Project Web Access, you need to detail these tasks in a manner that allows for assignment of resources and promotion to a project plan. What should you do?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Create a proposal, and then assign resources to tasks.
B.
Create a Microsoft SharePoint task list, and then make it visible to senior management.
C.
Create a Microsoft SharePoint task list, and then make it visible to the relevant resources.
D.
Add tasks to your timesheet to show the proposed work.