PrepAway - Latest Free Exam Questions & Answers

During the testing of the business continuity plan (BCP), which of the following methods of results analysis p

During the testing of the business continuity plan (BCP), which of the following methods of results analysis provides the BEST assurance that the plan is workable?

A. Measurement of accuracy

B. Elapsed time for completion of critical tasks

C. Quantitatively measuring the results of the test

D. Evaluation of the observed test results

It is important to have ways to measure the success of the plan and tests against the stated objectives. Therefore, results must be quantitatively gauged as opposed to an evaluation based only on observation. Quantitatively measuring the results of the test involves a generic statement measuring all the activities performed during BCP, which gives the best assurance of an effective plan. Although choices A and B are also quantitative, they relate to specific areas, or an analysis of results from one viewpoint, namely the accuracy of the results and the elapsed time.

Source: Information Systems Audit and Control Association, Certified Information Systems Auditor 2002 review manual, Chapter 5: Disaster Recovery and Business Continuity (page 269).


Leave a Reply