which of the following risk response techniques to resolve the issue?

An important team member will not be available to complete a project. The project manager
selects a new team member and trains the new team member on the project tasks. The project
manager is using which of the following risk response techniques to resolve the issue?

PrepAway - Latest Free Exam Questions & Answers

A.
Monitor the risk

B.
Mitigation of the risk

C.
Acceptance of the risk

D.
Transference of the risk

Explanation: